• The client on this project was YMCA Nottinghamshire.
  • There were two pitches both 7420m2 with a 50mm pile 3G sand/rubber filled carpet including line markings for Football.
  • All works were completed on time in a 16 week timescale.
  • Approximately, the project came to the value of £1,226,035.00 + VAT.
  • This was a brand new construction on a recreation ground, so a full installation was required the extent of which included excavations, installation of the drainage, sub base kerbs and macadam.
  • A new fencing scheme consisted of 4.50m high standard bar fencing, 4.5m high twin bar fencing with rebound panel, 1.2m high spectator fencing, 1 no. 1.20m wide x 1.20m high single leaf gate, 3 no. 3.00m wide 1.20m high pair of double leaf gate, and 1 no. pitch divider. Acoustic boundary fencing.
  •  
  • A new floodlighting scheme of a 15m high, 12 column, 200 lux floodlighting scheme.
  • Additionally, new sets of football goals were erected to complete the installation, litter bins, boot wipers and a set of flags.